Kodak's Exit 408 Is Sized for an Average Day at Exit 407. The Busiest Weekends Are a Different Math Problem.

"It's one of the busiest interchanges in the entire state, but that isn't all just tourists," TDOT Regional Communications Officer Mark Nagi told The Mountain Press at the September 15 open house for the proposed I-40 Exit 408. "These are people who live in Sevier County and live in the surrounding counties as well."

That description fits anyone who drives Winfield Dunn Parkway out of Kodak to reach the interstate. The new interchange would sit about 1.75 miles east of Exit 407, and the traffic numbers released in September are measured against Exit 407's average day.

The Number the Plan Is Built Around

City of Sevierville figures reported by The Mountain Press put Exit 407's current traffic at 56,000 to 60,000 vehicles a day. Once Exit 408 opens, the city projects that about 30% of that traffic would move to the new exit. Nagi gave a similar figure, saying more than 57,000 vehicles a day use Exit 407.

The same report gives a third number. Over the July 4th weekend in 2026, Exit 407 hit a peak of 99,604 vehicles in one day.

Put those figures together and the scale of the relief becomes clear. The table below is simple arithmetic on the published numbers, not a TDOT forecast.

Scenario at Exit 407 Vehicles per day
Average day today, City of Sevierville range 56,000 to 60,000
30% of that average day shifted to Exit 408 about 16,800 to 18,000
Average day left at Exit 407 after the shift about 39,200 to 42,000
July 4th weekend 2026 peak 99,604
That peak with 30% shifted, if the same share held about 69,700

The last row is the important one. Suppose a holiday weekend shifted the same share of cars that an average day does. Exit 407 would still carry roughly 10,000 more vehicles than it does on a typical day now. On an ordinary day, the arithmetic points to a real change for a Kodak driver. On the Fourth of July, the interchange would still be busier than its current normal.

One Letter Grade on Each Road

Traffic engineers grade roads with a level-of-service scale, and the city's projections use it. With traffic split between the two exits, the I-40 mainline would improve from LOS E to LOS D, and SR-66 would improve from LOS D to LOS C, according to the Mountain Press report.

That means each road moves up one grade. The projections describe an interchange that runs closer to its ideal, which is the same goal city officials stated when explaining why they reopened the conversation.

Why Exit 407 Needs Help After Its Own Redesign

Exit 407 already got a diverging diamond, and Sevierville City Administrator Dustin Smith told The Mountain Press that the redesign hasn't been enough. "While the 407 interchange and those intersections are not operating at necessarily a capacity, they are operating at a deficiency from what would be the most ideal and optimal operational standpoint," he said.

Smith said the project gained new urgency when the Eastern Band of Cherokee Indians bought the 200-plus-acre former Dumplin Creek property, the site anchored by Buc-ee's, and laid out "expansive plans" for it. He said that planned spur development is why Exit 407 needs relief if it is going to handle more traffic. Sevier County Mayor Bryan McCarter told the paper that Exit 408 "has been in front of the joint transportation committee for probably several decades now," and that the county needs infrastructure for both growth and the volume of traffic already on the corridor.

That puts the 30% figure in a new light. The new exit is expected to take some of today's traffic, while development near Exit 407 adds more. The Mountain Press summed it up directly: traffic capacity will keep rising as that area develops, even with the new interchange. Smith also pointed to the holiday-weekend risk of traffic backing up onto I-40 itself.

What Gets Built Besides the Ramp

According to the TDOT project page, the build alternative has four design elements:

  1. A new diverging diamond interchange at Exit 408, a design The Mountain Press describes as similar to the one at Exit 407.
  2. A north-south Connector Road from East Dumplin Valley Road, through the new interchange, to SR-139, Douglas Dam Road. TDOT describes it as a four- to eight-lane divided, limited-access road.
  3. Gateway Boulevard, a new east-west road along the southern edge of I-40 that meets Connector Road about 0.2 miles south of the interchange.
  4. A 10-foot greenway along Bryan Road that passes under I-40 and then follows Gateway Boulevard and Connector Road to Douglas Dam Road.

The plan also adds three new traffic signals: at Connector Road and East Dumplin Valley Road, at Connector Road and Gateway Boulevard, and at Connector Road and Douglas Dam Road. The whole build covers about 1.59 miles.

The fourth item matters most to Kodak residents who rarely get on I-40. A greenway that passes under the interstate creates a walking and biking link between the two sides of I-40 along Bryan Road. Nagi described it to The Mountain Press as a path designed to "pass under I-40, connect to Gateway Boulevard and continue alongside the new connector road."

Gateway Boulevard leaves an open question. TDOT's September presentation says its segment would run west about 0.82 miles, and the rest would be finished "as part of a future project by others." The meeting materials don't say who that is or where the road will end up.

What People Said at the Convention Center

The open house took place at the Sevierville Convention Center, 202 Gists Creek Road, and reactions there were mixed. WBIR reported that one resident asked whether the project would create more traffic. Another objected to turning a small country road into a four-lane highway and suggested SR-338 as an alternative. A Kodak native who drives for Uber told the station he supported the added capacity because it could make local trips easier. WBIR also reported that TDOT gave no estimate of how many homes might be affected.

WVLT reported a concern that the new exit sits too close to Exit 407 and could create an entertainment-district traffic problem. Sevier County EMS Director Rick Valentine supported adding routes. He also asked TDOT to extend road improvements west toward Highway 66, near an EMS and fire station, because congestion at Exit 407 affects response times. His request brings the traffic back to Exit 407 itself, where the peak-day math above plays out.

The Calendar Between Now and a New Ramp

Here is the timeline TDOT and local coverage have published so far:

  • September 15, 2026: Public information meeting held.
  • October 6, 2026: Comment deadline for the official meeting summary. Comments received by then go into the Environmental Assessment.
  • Quarter 1 of 2027: Environmental Assessment expected for public review, with a public hearing tentatively scheduled.
  • 2027: Right-of-way acquisition expected to begin. Nagi said it "would likely take a couple of years."
  • Fiscal Year 2030: Estimated construction start in TDOT's 10-Year Project Plan.
  • Completion: Listed as TBD.

Nagi told The Mountain Press that "funding is in place for this project right now." TDOT says the project is funded through its Statewide Partnership Program, with extra planning and funding support from Sevier County and the City of Sevierville. Sevier County submitted the project under that program in 2023. Because federal transportation money is involved, the Environmental Assessment must follow the National Environmental Policy Act, and it includes studies on traffic and safety, relocations, noise, recreational resources and visual impacts.

On that timeline, several more holiday seasons will run through Exit 407 as it is now. The next one is close. Smoky Mountain Winterfest runs from November 6, 2026, through February 15, 2027, with lights across Sevierville, Pigeon Forge and Gatlinburg. The Christmas at the Courthouse event is December 3, and Sevierville's 64th Annual Christmas Parade is December 5 at 11 a.m. These are the kinds of busy weekends Smith described as the risk Exit 408 is meant to reduce.

TDOT's comment line, 1-877-SmartWay, is listed on the project page, and the Q1 2027 hearing is the next chance for the public to weigh in. That hearing will also bring the first formal look at a preferred alternative and its environmental effects.

If you own a home or a rental near Douglas Dam Road, East Dumplin Valley Road or Bryan Road and want to know how a planned corridor affects access, guest drive times or long-term plans, Kelly White tracks the Exit 408 process alongside the local market and can walk you through what has been published so far. Sign up to Receive Listings & Investment Insights and you'll hear when the Environmental Assessment comes out.